2022-2027 Bond Project: Olmos Basin Park

2022-2027 Bond Project: Olmos Basin Park

The Olmos Basin Park Project will construct general park improvements within available funding which may include the installation of a permanent restroom to service the walking trail area of the park and improvements of the Farmer's Market area.

  • Project Type: Parks and Recreation
  • Phase: Construction
  • Estimated Construction Timeline: Winter 2025 - Winter 2026


Note: Estimated Timeline Construction Seasons are identified as: 

  • Winter (January, February, March)
  • Spring (April, May, June)
  • Summer (July, August, September)
  • and Fall (October, November, December.)

Budget

  • 2022 General Obligation Bond (Parks): $1,250,000.00
  • Tree Mitigation Fund: $35,000                                       
  • Total: $1,250,000.00

Updates

Construction Notice
Public Works, Parks & Recreation, and City Council District 1 are excited to announce the ongoing construction on the improvements to Phase 1 of Olmos Basin Park, made possible by the 2022-2027 Bond Program. Phase 1 includes improvements at the Shearer Hills/Ridgeview Walking Trail area of the park.

The project will include a new premanufactured restroom, new water line and new playground.

Project Timeline: Winter 2025 - Fall 2025